Commercial Solar for Manufacturing
Commercial Winchester 12kW Array

Commercial Solar for Manufacturing

Client: Winchester Joinery Ltd
Completed: October 2024

01The Challenge

A busy joinery workshop with high daytime electricity usage from machinery. They were facing soaring energy bills that were eating into their profit margins.

02Our Solution

We designed a 12kW 3-phase system using high-wattage 585W Jinko Commercial Modules. The system connects directly to their distribution board, offsetting the power used by saws and extraction units in real-time.

03The Outcome

The business has reduced its grid draw by 60% during operating hours. The system is projected to pay for itself in just 3.8 years thanks to the high self-consumption rate.

26%

ROI

3.8 Years

Payback

2.8 Tons/yr

CO2 Saved

Inspired by this project?

We can design a similar high-performance system tailored to your property in Winchester.